| Chezcore, Inc. was called
upon to perform a major renovation project for the Detroit Public
Schools to a portion of the Hutchins Elementary/Smith Academy. The
renovated wing is called "The Smith Academy". The Smith
Academy was built because of a special education mandate from the
state.
The timeline of the project required that
Chezcore, Inc. complete the renovation of over 40,000 square feet
of space within a 42-calendar day schedule. Despite a 18-day delay
due to abatement, the classrooms and bathrooms were completed on
time. The students were in the finished classrooms on the first
day of school!
|